MTIS is a local authority-led programme of retrofit works to private and council homes in Lochend, Edinburgh. I am an owner-occupier, and the only private owner in my block. The council determines the programme timetable, scope of works, procurement, sequencing and cost. My home is in Phase 6. This site records the delays, changing dates and repeated failures that have kept my life on hold.
PROGRAMME ANNOUNCED
14 JULY 2023
TIME I'VE BEEN WAITING FOR THE WORKS TO START IN MY FLAT
0
DAYS
:
00
HOURS
:
00
MINUTES
:
00
SECONDS
And counting.
This is an unofficial tracking project. Not affiliated with the City of Edinburgh Council.
PROGRAMME RECORD
A sad record of announcements, delays and other retrofit misadventures.